G.R. No. 141897 September 24, 2001 METRO CONSTRUCTION, INC., petitioner, vs. CHATHAM PROPERTIES, INC., respondent.
FACTS : Respondent Chatham Properties, Inc. (CHATHAM) and petitioner Metro Construction, Inc. (MCI) entered into a contract for the construction of a multi-storey building known as the Chatham House. In April 1998, MCI sought to collect from CHATHAM a sum of money for unpaid progress billings and other charges and instituted a request for adjudication of its claims with the CIAC. The preliminary conference before the CIAC started in June 1998 and was concluded a month after with the signing of the Terms of Reference (TOR) of the Case. In the meantime, the TOR was amended and finalized on 19 August 1998. The facts, as admitted by the parties before the CIAC and incorporated in the original TOR, are as follows :
FACTS : Respondent Chatham Properties, Inc. (CHATHAM) and petitioner Metro Construction, Inc. (MCI) entered into a contract for the construction of a multi-storey building known as the Chatham House. In April 1998, MCI sought to collect from CHATHAM a sum of money for unpaid progress billings and other charges and instituted a request for adjudication of its claims with the CIAC. The preliminary conference before the CIAC started in June 1998 and was concluded a month after with the signing of the Terms of Reference (TOR) of the Case. In the meantime, the TOR was amended and finalized on 19 August 1998. The facts, as admitted by the parties before the CIAC and incorporated in the original TOR, are as follows :
1. On 21 April 1994, the parties formally
entered into a contract for the construction of the "Chatham House" .
. . for the contract price of price of P50,000,000.00
2. On 12 July 1994, a Supplemental Contract
was executed by and between the parties whereby CHATHAM authorized MCI to
procure in behalf of the former materials, equipment, etc.
3. Under Section I.04 of the Supplemental Contract,
the total amount of procurement and transportation cost[s] and expenses which
may be reimbursed by MCI from CHATHAM shall not exceed the amount of P75,
000,000.00.
4. In the course of the construction, Change
Orders No. 1, 4, 8A, 11, 12 and 13 were implemented,
5. CHATHAM reimbursed MCI the amount of
P60,000.00 corresponding to bonuses advanced to its workers by the latter for
the 14th, 16th, and 17th floors.
6. CHATHAM's payments to MCI totaled
P104,875,792.37, representing payments for portions of MCI's progress billings
and x x x additional charges..
In the resolution of these issues, the CIAC
discovered significant data, which were not evident or explicit in the
documents and records but otherwise revealed or elicited during the hearings,
which the CIAC deemed material and relevant to the complete adjudication of the
case
The CIAC disposed of the specific money
claims by either granting or reducing them. On Issue No. 9, i.e., whether
CHATHAM failed to complete and/or deliver the project within the approved
completion period and, if so, whether CHATHAM is liable for liquidated damages
and how much.
CIAC rendered JUdgement in favor of the
Claimant [MCI] directing Respondent [CHATHAM] to pay Claimant [MCI] the net sum
of SIXTEEN MILLION ONE HUNDRED TWENTY SIX THOUSAND NINE HUNDRED TWENTY TWO
& 91/100 (16,126,922.91) PESOS. Impugning the decision of the CIAC, CHATHAM
instituted a petition for review with the Court of Appeals
In upholding the decision of the CIAC, the
Court of Appeals confirmed the jurisprudential principle that absent any
showing of arbitrariness, the CIAC's findings as an administrative agency and
quasi judicial body should not only be accorded great respect but also given
the stamp of finality. However the Court of Appeals found exception in the
CIAC's disquisition of Issue No.9 on the matter of liquidated damages.
ISSUE : WON under existing
law and rules the Court of Appeals can also review findings of facts of the
Construction Industry Arbitration Commission (CIAC)
HELD : EO. No. 1008 vest
upon the CIAC original and exclusive jurisdiction over disputes arising from,
or connected with, contracts entered into by parties involved in construction
in the Philippines, whether the dispute arises before or after the completion
of the contract, or after the abandonment or breach thereof. By express
provision of Section 19 thereof, the arbitral award of the CIAC is final and
unappealable, except on questions of law, which are appealable to the Supreme
Court.
The parties, however, disagree on whether the
subsequent Supreme Court issuances on appellate procedure and R.A. No. 7902
removed from the Supreme Court its appellate jurisdiction in Section 19 of E.O.
No. 1008 and vested the same in the Court of Appeals, and whether appeals from
CISC awards are no longer confined to questions of law.
Through Circular No. 1-91, the Supreme Court
intended to establish a uniform procedure for the review of the final orders or
decisions of the Court of Tax Appeals and other quasi judicial. The Circular
designated the Court of Appeals as the reviewing body to resolve questions of
fact or of law or mixed questions of fact and law.
It is clear that Circular No. 1-91 covers the
CIAC. In the first place, it is a quasi judicial agency. In the second place,
the language of Section 1 of Circular No. 1-91 emphasizes the obvious inclusion
of the CIAC even if it is not named in the enumeration of quasi-judicial
agencies. In sum, under Circular No. 1-91, appeals from the arbitral awards of
the CIAC may be brought to the Court of Appeals, and not to the Supreme Court
alone. The grounds for the appeal are likewise broadened to include appeals on
questions of facts and appeals involving mixed questions of fact and law
No comments:
Post a Comment