Wednesday, July 20, 2016

CASE DIGEST : METRO CONSTRUCTION vs CHATHAM PROPERTIES

G.R. No. 141897  September 24, 2001  METRO CONSTRUCTION, INC., petitioner, vs. CHATHAM PROPERTIES, INC., respondent.

FACTS : Respondent Chatham Properties, Inc. (CHATHAM) and petitioner Metro Construction, Inc. (MCI) entered into a contract for the construction of a multi-storey building known as the Chatham House. In April 1998, MCI sought to collect from CHATHAM a sum of money for unpaid progress billings and other charges and instituted a request for adjudication of its claims with the CIAC. The preliminary conference before the CIAC started in June 1998 and was concluded a month after with the signing of the Terms of Reference (TOR) of the Case. In the meantime, the TOR was amended and finalized on 19 August 1998. The facts, as admitted by the parties before the CIAC and incorporated in the original TOR, are as follows :
1. On 21 April 1994, the parties formally entered into a contract for the construction of the "Chatham House" . . . for the contract price of price of P50,000,000.00
2. On 12 July 1994, a Supplemental Contract was executed by and between the parties whereby CHATHAM authorized MCI to procure in behalf of the former materials, equipment, etc.
3. Under Section I.04 of the Supplemental Contract, the total amount of procurement and transportation cost[s] and expenses which may be reimbursed by MCI from CHATHAM shall not exceed the amount of P75, 000,000.00.
4. In the course of the construction, Change Orders No. 1, 4, 8A, 11, 12 and 13 were implemented,
5. CHATHAM reimbursed MCI the amount of P60,000.00 corresponding to bonuses advanced to its workers by the latter for the 14th, 16th, and 17th floors.
6. CHATHAM's payments to MCI totaled P104,875,792.37, representing payments for portions of MCI's progress billings and x x x additional charges..
In the resolution of these issues, the CIAC discovered significant data, which were not evident or explicit in the documents and records but otherwise revealed or elicited during the hearings, which the CIAC deemed material and relevant to the complete adjudication of the case

The CIAC disposed of the specific money claims by either granting or reducing them. On Issue No. 9, i.e., whether CHATHAM failed to complete and/or deliver the project within the approved completion period and, if so, whether CHATHAM is liable for liquidated damages and how much.

CIAC rendered JUdgement in favor of the Claimant [MCI] directing Respondent [CHATHAM] to pay Claimant [MCI] the net sum of SIXTEEN MILLION ONE HUNDRED TWENTY SIX THOUSAND NINE HUNDRED TWENTY TWO & 91/100 (16,126,922.91) PESOS. Impugning the decision of the CIAC, CHATHAM instituted a petition for review with the Court of Appeals

In upholding the decision of the CIAC, the Court of Appeals confirmed the jurisprudential principle that absent any showing of arbitrariness, the CIAC's findings as an administrative agency and quasi judicial body should not only be accorded great respect but also given the stamp of finality. However the Court of Appeals found exception in the CIAC's disquisition of Issue No.9 on the matter of liquidated damages.

ISSUE : WON under existing law and rules the Court of Appeals can also review findings of facts of the Construction Industry Arbitration Commission (CIAC)

HELD : EO. No. 1008 vest upon the CIAC original and exclusive jurisdiction over disputes arising from, or connected with, contracts entered into by parties involved in construction in the Philippines, whether the dispute arises before or after the completion of the contract, or after the abandonment or breach thereof. By express provision of Section 19 thereof, the arbitral award of the CIAC is final and unappealable, except on questions of law, which are appealable to the Supreme Court.

The parties, however, disagree on whether the subsequent Supreme Court issuances on appellate procedure and R.A. No. 7902 removed from the Supreme Court its appellate jurisdiction in Section 19 of E.O. No. 1008 and vested the same in the Court of Appeals, and whether appeals from CISC awards are no longer confined to questions of law.

Through Circular No. 1-91, the Supreme Court intended to establish a uniform procedure for the review of the final orders or decisions of the Court of Tax Appeals and other quasi judicial. The Circular designated the Court of Appeals as the reviewing body to resolve questions of fact or of law or mixed questions of fact and law.

It is clear that Circular No. 1-91 covers the CIAC. In the first place, it is a quasi judicial agency. In the second place, the language of Section 1 of Circular No. 1-91 emphasizes the obvious inclusion of the CIAC even if it is not named in the enumeration of quasi-judicial agencies. In sum, under Circular No. 1-91, appeals from the arbitral awards of the CIAC may be brought to the Court of Appeals, and not to the Supreme Court alone. The grounds for the appeal are likewise broadened to include appeals on questions of facts and appeals involving mixed questions of fact and law

The jurisdiction of the Court of Appeals over appeals from final orders or decisions of the CIAC is further fortified by the amendments to B.P. Blg. 129, as introduced by RA. No. 7902. With the amendments, the Court of Appeals is vested with appellate jurisdiction over all final judgments, decisions, resolutions, orders or awards of Regional Trial Courts and quasi-judicial agencies, instrumentalities, boards or commissions, except "those within the appellate jurisdiction of the Supreme Court in accordance with the Constitution, the Labor Code of the Philippines under Presidential Decree No. 442, as amended, the provisions of this Act, and of subparagraph (1) of the third paragraph and subparagraph (4) of the fourth paragraph of Section 17 of the Judiciary Act of 1948.".  In view of all the foregoing, The Supreme Court rejects MCI's submission that Circular No. 1-91, B.P. Blg. 129, as amended by RA. 7902, Revised Administrative Circular 1-95, and Rule 43 of the 1997 Rules of Civil Procedure failed to efficaciously modify the provision on appeals in E.O. No. 1008.

No comments:

Post a Comment