G.R. No. 159795 July 30, 2004 SPOUSES ROBERTO & EVELYN DAVID and COORDINATED GROUP, INC., petitioners, vs. CONSTRUCTION INDUSTRY AND ARBITRATION COMMISSION and SPS. NARCISO & AIDA QUIAMBAO, respondents.
FACTS : Petitioner COORDINATED GROUP, INC. (CGI) is a corporation engaged in the construction business, with petitioner-spouses ROBERTO and EVELYN DAVID as its President and Treasurer, respectively. respondent-spouses NARCISO and AIDA QUIAMBAO engaged the services of petitioner CGI to design and construct a five-storey concrete office/residential building on their land in Tondo, Manila. The Design/Build Contract of the parties provided that:
FACTS : Petitioner COORDINATED GROUP, INC. (CGI) is a corporation engaged in the construction business, with petitioner-spouses ROBERTO and EVELYN DAVID as its President and Treasurer, respectively. respondent-spouses NARCISO and AIDA QUIAMBAO engaged the services of petitioner CGI to design and construct a five-storey concrete office/residential building on their land in Tondo, Manila. The Design/Build Contract of the parties provided that:
(a)
petitioner CGI shall prepare the working drawings for the construction project;
(b)
respondents shall pay petitioner CGI the sum of Seven Million Three Hundred Nine Thousand Eight
Hundred Twenty-One and 51/100
Pesos (P7,309,821.51) for the construction of the building, including the costs of labor, materials
and equipment, and Two Hundred
Thousand Pesos (P200,000.00) for the cost of the design; and
(c)
the construction of the building shall be completed within nine (9) months after
securing the building permit.
The completion of the construction was
initially scheduled on or before July 16, 1998 but was extended to November 15,
1998 upon agreement of the parties but petitioners failed to follow the
specifications and plans as previously agreed upon. Respondents demanded the
correction of the errors but petitioners failed to act on their complaint.
Consequently, respondents rescinded the contract on October 31, 1998, after
paying 74.84% of the cost of construction
Respondents then engaged the services of
another contractor, RRA and Associates, It was found that petitioners revised
and deviated from the structural plan of the building without notice to or
approval by the respondents.
Respondents filed a case for breach of
contract against petitioners before the Regional Trial Court (RTC) of Manila.
At the pre-trial conference, the parties agreed to submit the case for
arbitration to CIAC. The RTC of Manila then dismissed the case and transmitted
its records to the CIAC.
The arbitrator rendered judgment against
petitioners. Petitioners appealed to the Court of Appeals which affirmed the
arbitrator’s Decision but deleted the award for lost rentals
ISSUE
: WON THE FACTUAL FINDINGS OF CIAC ARE FINAL AND CONCLUSIVE AND NOT REVIEWABLE
BY THE SUPREME COURT ON APPEAL.
HELD: Executive Order No.
1008 entitled, "Construction Industry Arbitration Law" provided for
an arbitration mechanism for the speedy resolution of construction disputes
other than by court litigation. It recognized the role of the construction
industry in the country’s economic progress as it utilizes a large segment of
the labor force and contributes substantially to the gross national product of
the country. Thus, E.O. No. 1008 vests on the CIAC original and exclusive
jurisdiction over disputes arising from or connected with construction
contracts entered into by parties who have agreed to submit their case to voluntary
arbitration. Section 19 of E.O. No. 1008 provides that its arbitral award shall
be appealable to the Supreme Court only on questions of law.
There is a question of law when the doubt or
difference in a given case arises as to what the law is on a certain set of
facts, and there is a question of fact when the doubt arises as to the truth or
falsity of the alleged facts.
In the case at bar, it is readily apparent
that petitioners are raising questions of fact. In their first assigned error,
petitioners claim that at the time of rescission, they had completed 80% of the
construction work and still have 15 days to finish the project. They likewise
insist that they constructed the building in accordance with the contract and
any modification on the plan was with the consent of the respondents. The
second assigned error likewise involves a question of fact. It is contended
that petitioner-spouses David cannot be held jointly and severally liable with
petitioner CGI in the payment of the arbitral award as they are merely its corporate
officers
Clearly, the case at bar does not raise any
genuine issue of law. We reiterate the rule that factual findings of
construction arbitrators are final and conclusive and not reviewable by this
Court on appeal, except when the petitioner proves affirmatively that: (1) the
award was procured by corruption, fraud or other undue means; (2) there was
evident partiality or corruption of the arbitrators or of any of them; (3) the
arbitrators were guilty of misconduct in refusing to postpone the hearing upon
sufficient cause shown, or in refusing to hear evidence pertinent and material
to the controversy; (4) one or more of the arbitrators were disqualified to act
as such under section nine of Republic Act No. 876 and willfully refrained from
disclosing such disqualifications or of any other misbehavior by which the
rights of any party have been materially prejudiced; or (5) the arbitrators
exceeded their powers, or so imperfectly executed them, that a mutual, final
and definite award upon the subject matter submitted to them was not made.12
Petitioners failed to show that any of these exceptions applies to the case at
bar.
No comments:
Post a Comment