Wednesday, July 20, 2016

CASE DIGEST : SPOUSES DAVID vs CONSTRUCTION INDUSTRY AND ARBITRATION COMMISSION (CIAC)

G.R. No. 159795 July 30, 2004  SPOUSES ROBERTO & EVELYN DAVID and COORDINATED GROUP, INC., petitioners, vs. CONSTRUCTION INDUSTRY AND ARBITRATION COMMISSION and SPS. NARCISO & AIDA QUIAMBAO, respondents.

FACTS : Petitioner COORDINATED GROUP, INC. (CGI) is a corporation engaged in the construction business, with petitioner-spouses ROBERTO and EVELYN DAVID as its President and Treasurer, respectively. respondent-spouses NARCISO and AIDA QUIAMBAO engaged the services of petitioner CGI to design and construct a five-storey concrete office/residential building on their land in Tondo, Manila. The Design/Build Contract of the parties provided that:

(a) petitioner CGI shall prepare the working drawings for the construction project;
(b) respondents shall pay petitioner CGI the sum of Seven Million Three Hundred Nine Thousand Eight Hundred Twenty-One and 51/100 Pesos (P7,309,821.51) for the construction of the building,  including the costs of labor, materials and equipment, and Two Hundred Thousand Pesos (P200,000.00) for the cost of the design; and
 (c) the construction of the building shall be completed within nine (9) months after securing the building permit.

The completion of the construction was initially scheduled on or before July 16, 1998 but was extended to November 15, 1998 upon agreement of the parties but petitioners failed to follow the specifications and plans as previously agreed upon. Respondents demanded the correction of the errors but petitioners failed to act on their complaint. Consequently, respondents rescinded the contract on October 31, 1998, after paying 74.84% of the cost of construction

Respondents then engaged the services of another contractor, RRA and Associates, It was found that petitioners revised and deviated from the structural plan of the building without notice to or approval by the respondents.

Respondents filed a case for breach of contract against petitioners before the Regional Trial Court (RTC) of Manila. At the pre-trial conference, the parties agreed to submit the case for arbitration to CIAC. The RTC of Manila then dismissed the case and transmitted its records to the CIAC.
The arbitrator rendered judgment against petitioners. Petitioners appealed to the Court of Appeals which affirmed the arbitrator’s Decision but deleted the award for lost rentals

ISSUE : WON THE FACTUAL FINDINGS OF CIAC ARE FINAL AND CONCLUSIVE AND NOT REVIEWABLE BY THE SUPREME COURT ON APPEAL.

HELD: Executive Order No. 1008 entitled, "Construction Industry Arbitration Law" provided for an arbitration mechanism for the speedy resolution of construction disputes other than by court litigation. It recognized the role of the construction industry in the country’s economic progress as it utilizes a large segment of the labor force and contributes substantially to the gross national product of the country. Thus, E.O. No. 1008 vests on the CIAC original and exclusive jurisdiction over disputes arising from or connected with construction contracts entered into by parties who have agreed to submit their case to voluntary arbitration. Section 19 of E.O. No. 1008 provides that its arbitral award shall be appealable to the Supreme Court only on questions of law.
There is a question of law when the doubt or difference in a given case arises as to what the law is on a certain set of facts, and there is a question of fact when the doubt arises as to the truth or falsity of the alleged facts.

In the case at bar, it is readily apparent that petitioners are raising questions of fact. In their first assigned error, petitioners claim that at the time of rescission, they had completed 80% of the construction work and still have 15 days to finish the project. They likewise insist that they constructed the building in accordance with the contract and any modification on the plan was with the consent of the respondents. The second assigned error likewise involves a question of fact. It is contended that petitioner-spouses David cannot be held jointly and severally liable with petitioner CGI in the payment of the arbitral award as they are merely its corporate officers


Clearly, the case at bar does not raise any genuine issue of law. We reiterate the rule that factual findings of construction arbitrators are final and conclusive and not reviewable by this Court on appeal, except when the petitioner proves affirmatively that: (1) the award was procured by corruption, fraud or other undue means; (2) there was evident partiality or corruption of the arbitrators or of any of them; (3) the arbitrators were guilty of misconduct in refusing to postpone the hearing upon sufficient cause shown, or in refusing to hear evidence pertinent and material to the controversy; (4) one or more of the arbitrators were disqualified to act as such under section nine of Republic Act No. 876 and willfully refrained from disclosing such disqualifications or of any other misbehavior by which the rights of any party have been materially prejudiced; or (5) the arbitrators exceeded their powers, or so imperfectly executed them, that a mutual, final and definite award upon the subject matter submitted to them was not made.12 Petitioners failed to show that any of these exceptions applies to the case at bar.

No comments:

Post a Comment